Schedule
The official milestones, as given in the Management Plan, are listed below.
Kick-Off | 04 June 2004 |
ESO Council Approval | 23 May 2005 |
Preliminary Design Review | 11 May 2006 |
Final Design Review | 24 April 2008 |
Test Readiness Review | November 2010 |
Preliminary Acceptance Review in Europe | March 2011 |
Provisional Acceptance in Chile | September 2011 |